Summary of tasks

Milestones

Gantt Charts

Summary of tasks

The first phase of the Ozone_cci project was kicked off on September, 1st, 2010. The second phase of the Ozone_cci project was kicked off on March, 24th, 2014.

The work has been subdivided into 6 major tasks:

  • Project Management
  • Requirement Management
  • Algorithm Development
  • System Evolution & Product Generation
  • Product Validation
  • Climate Assessment

Each phase is structured into three contractual periods, each of 12 months.

Phase I

Activities of year 1 (September 2010 - August 2011):

  • Requirements analysis and product specifications
  • Algorithm development, intercomparisons and selection
  • System specifications

Activities of year 2 (November 2011 - October 2012):

  • Algorithm development, intercomparisons and selection
  • System prototyping and ECV production
  • System specifications

Activities of year 3 (November 2012 - December 2013):

  • System prototyping and ECV production
  • Final product validation and user assessment
  • System specifications

 

Milestones

In following table, the planned milestones to be achieved are summarized.

Month Result
September 2010 Project Kick Off
February 2011

Identification of

User Requirements
Product Specifications
Data Access Requirements

May 2011

Finalization of

Product Validation Plan
Data Base for task 2 (algorithm development, intercomparisons and selection)

August 2011

Finalization of

Algorithm Theoretical Basis Document (version 0)
Initial Round Robin Data Package
Product validation and selection report (version 1)
Input output data definition document
System requirements document

April 2012

Finalization of

Round Robin Data Package (final)
Product validation and selection report (version 2)
Algorithm theoretical basis document (version 1)
Input Output data definition (version 1)
Data base for task 3 (system prototyping and ECV production)
System Specifications

July 2012

Finalization of

Description of system prototype
System verification

October 2012

Finalization of

Product User Guide
Climate Research Data Package (initial)
Algorithm Theoretical basis document (version 1)

June 2013

Finalization of

Climate Research Data Package (final)
Algorithm Theoretical Basis Document (version 2)
Detailed processing model
Input Output Data Definition (version 2)

September 2013

Finalization of

Product Validation and Intercomparision Report
System Specification (version 1)

December 2013

Finalization of

Climate Assessment Report
Final report of the project

 

The Gantt charts:


are available in attached documents, per contractual phase.

AttachmentSize
ozone_cci_gantt_phase3.png14.37 KB
ozone_cci_gantt_phase1_completed.gif29.14 KB
ozone_cci_gantt_phase2.gif31.44 KB
Ozone_cci_phase_2_gantt_planning.gif75.23 KB